Version 2 (modified by Yves, 10 years ago) ( diff )

--

Standard schedule

  1. Day 0: Feature freeze
  2. Day 3: String freeze
  3. Day 6: Translation freeze
  4. Day 6: Commit freeze
  5. Day 7: Packaging
  6. Day 9: Release

Phases

Name Tasks to complete
Development
Feature freeze
String freeze
Translation freeze
Packaging
Release

Release progress table

Put your name into the "Accepted by" column to take over a task and agree to completed it in time (according to the "Deadline" column). Update the status column regularly enough to keep team member informed. Especially note if you are waiting for input or are otherwise prevented from working on the task.

Next release: Alpha 17

Task shortname Accepted by Deadline Status
Start release process

Task descriptions

Start release process

Description:
The team decides that there are enough new features and that it's time to release a new alpha version. Usually in a team meeting, we decide when the regular schedule starts and if there are any differences to the predefined schedule.
Can be completed in phase: Development
Candidates: Whole team (usually at the meeting)

Update release progress on Trac

Description:
Remove all content from the Release progress table and replace "Next release" with the right version number.
Can be completed in phase: Development
Candidates: Everyone